Magnolia Drive Trail, Phase II
Phase II, Pontiac to Diamond, is complete and opened to the public in January 2026.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Blueprint is the joint City of Tallahassee and Leon County infrastructure program, and its board is made up of city and county commissioners. Every project moves through five stages. Five filled blocks means done.
Nothing in that combination yet. Try another side of town or status.
Phase II, Pontiac to Diamond, is complete and opened to the public in January 2026.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
A 1.2-mile trail, completed April 2026.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Springhill Road from Capital Circle to south of Windy Pines Lane. Construction completed June 2026. The rest of Airport Gateway is in design and right-of-way acquisition.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Roadway construction completed June 2026, with landscaping still underway. FDOT funded construction.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Single-track trail construction completed April 2026.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Northeast Gateway, south of I-10. Construction began Nov. 6, 2023. The I-10 bridge began June 22, 2025.
Done byEarly 2027 anticipated. Bridge mid-2027.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Under construction, including the Community Building.
OpensMid-2027 anticipated.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Under construction. The city-led Southside Transit Center next door is also under construction.
Done byLate 2026 anticipated.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Construction began January 2025.
Done byEarly 2027 anticipated.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Under construction. FDOT funded construction.
$231.1M FDOT + Blueprint, whole corridorDone byMid-2030 estimated.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Phase III, Diamond to Apalachee. Design is 90% complete and right-of-way acquisition is ongoing.
NextConstruction anticipated early 2027.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Northeast Corridor Connector. Design underway. Right-of-way purchases began in 2024.
NextPhase 1 construction anticipated 2026, done late 2027. Phase 2 done 2030.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
In permitting.
NextConstruction procurement expected late 2026.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Design began in 2025 and is on hold.
Waiting onLease negotiations between Leon County and the North Florida Fair Association.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
Planning study completed May 2026. Blueprint planned to hire designers in fall 2026. On Oct. 30, USDOT awarded $23.5 million for the first segment.
NextBoard meeting Nov. 12. Construction expected 2030.
As of Oct. 30, 2026 · Blueprint Q3 2026 report · USDOT grant report
Listed by Blueprint as not yet initiated.
As of Sept. 1, 2026 · Blueprint Q3 2026 report
What's included: 16 physical projects from Blueprint's Q3 2026 report, chosen to cover every side of town. Studies and funding programs without a single build site are left out. Missing one you care about? Email builtfortlh@gmail.com and I'll add it. The city and Blueprint don't publish a percent complete for projects in progress, so this tracker doesn't either. 100% appears only when a project is done. Stages and dates are Blueprint's own wording, "anticipated" included, checked line by line against the report on Nov. 1, 2026. Spot something out of date? Tell me and I'll check the source.
When a bar fills in on your side of town,
you'll hear it Sunday.
Tallahassee, in Plain English. Every Sunday, one email tells you what City Hall decided, what it costs, and what happens next. The first issue lands Sunday, November 8. One email every Sunday. No noise, no spam, unsubscribe anytime.
Three rules for everything on this site.
Every number links to the public document it came from. If there's no source, it isn't here.
Where a percentage doesn't exist, I don't invent one. Projects move through five stages, and 100% means done.
Every card shows the date of its source. When something changes or I get it wrong, the correction is explained publicly.
No corrections yet. When something here is wrong, it gets fixed and listed here with the date, what was wrong, and what changed.